Request a quoteA practical way to sort, log and answer consultant comments, revise the drawings and resubmit clearly. Written for joinery and millwork contractors, workshops and design firms.
When joinery or millwork shop drawings come back from the consultant, expect comments. Some are normal coordination questions. Some are required corrections. Some need a design decision, and some raise technical issues that stay open until the right people agree an answer. Not every comment is minor, and not every one is routine.
The risk is a slow or untracked response that brings the same questions back in a second round. This guide sets out a practical way to sort comments, log them, revise the drawings and resubmit clearly, for projects in the GCC, USA, Canada, UK and Australia. It describes general good practice: your contract and the consultant’s instructions always come first.

Watermarked sample sheet. See more approved previews.
Reviewers return drawings with a status and comments. The wording differs from project to project. Some use “Approved”, “Approved with comments” and “Revise and resubmit”; others use letter codes or their own phrases. Use the status codes in your own project documents.
Whatever the wording, the question that matters is whether fabrication may proceed. That is set by the project’s contract documents and the instructions of the responsible reviewers, not by the drafter. If the status or its effect is unclear, ask before anything is released to the workshop.
Read the whole return, then put each comment in one of five groups:
Corrections and clarifications can usually be handled by the drawing team. Design decisions, scope changes, conflicts and open technical issues should go back to the responsible person, with the sheet and detail marked, rather than being absorbed silently.
A comment log is a simple table that travels with each issue. For each comment it records what was said, what was done and where. Responses should show clearly whether a comment led to a drawing correction, was answered as a clarification, or is awaiting approval or a decision.
| Ref | Sheet / detail | Comment (as received) | Type | Response | Rev. | Status |
|---|---|---|---|---|---|---|
| 01 | Sheet 3, section A | Confirm fixing to wall | Clarification | Fixing method stated in the response and noted on the detail | B | Answered |
| 02 | Sheet 5, elevation | Panel height does not match the dimension on the plan | Drawing correction | Dimension revised and schedule updated | B | Revised |
| 03 | Sheet 2, plan | Finish to be confirmed by designer | Awaiting approval | Query sent to the designer | — | Open |
Illustrative example only. It is not taken from any client project.
Preparing and maintaining a comment log is part of our drafting service where it is included in the agreed scope.
Follow the submittal procedure in your project documents. As a general rule, a clear resubmission includes:
Agree one named contact on each side, and send questions together in one list with the drawing location marked, rather than scattered across emails.
Projects in the GCC and elsewhere often involve several reviewers. Depending on the project, the interior designer, the main contractor, the client’s representatives, building management or other consultants may all comment, and their comments are not always consistent. Some practical points:
Repeated comments often come from a few avoidable causes: a comment was only partly answered, a change that fixed one comment created a conflict elsewhere, or a change was made that nobody had asked for and nobody declared. A comment log and a full re-check before resubmitting help reduce avoidable omissions and repeated comments.
They cannot guarantee approval. A reviewer may raise new points on a resubmission, and the decision to approve always rests with the responsible reviewers.
We are a project-based outsourced technical drafting partner, coordinated from Jeddah, Saudi Arabia, with a Philippines-based drafting team.
Depending on the agreed scope, we:
We do not:
Delivery schedules depend on the agreed project scope and team availability, and are confirmed before work starts. Our Urth Caffé case study is an existing Portfolio example of a full numbered shop drawing set with site progress photographs. Approved, watermarked previews are on our Portfolio; additional samples are available on request, subject to client confidentiality and approval.
Yes, depending on the agreed scope and on the legibility and completeness of the comments supplied. A marked-up PDF or a comment sheet is the best starting point.
No. Design decisions stay with the designer and the responsible professionals. We flag them back to you with the drawing location marked.
We log both, mark the affected drawing location and send the conflict back for a decision, rather than choosing one silently.
Approval statuses, design changes and permission to proceed must follow the project’s contract documents and the instructions of the responsible reviewers. If the status or its effect is unclear, ask the reviewer or your contract administrator before releasing work.
The latest drawings in DWG, the consultant’s returned comments, the previous issue’s log if there is one, and any new design information received since.
Send a short brief and the returned comments through the quotation form or on WhatsApp at +966 565 362 134. We confirm scope and quote clearly before drafting starts.